04/26/2021 |
The (04/26/2021, C-141) application [22383] was accepted by OCD. The operator was emailed with details of this event. |
04/26/2021 |
An application [22383] was submitted to OCD for review. It was submitted, indicating that it was an: [C-141] Application for administrative approval of a release notification and corrective action The operator was emailed confirmation of this event. |
03/30/2021 |
The (04/26/2021, C-141) application [22383] was assigned to this incident. |
03/24/2021 |
The (03/24/2021, NOR) application [21826] was assigned to this incident. |
03/24/2021 |
Initial Response question & answers at the time of notification were as follows. - The source of the release has been stopped: True.
- The impacted area has been secured to protect human health and the environment: True.
- Released materials have been contained via the use of berms or dikes, absorbent pads, or other containment devices: True.
- All free liquids and recoverable materials have been removed and managed appropriately: True.
|
03/24/2021 |
New incident created by the operator, upon the submission of notification of release. |
03/15/2021 |
C-141 received on 3/30/2021 for release on 3/15/2021. The cause of the release was reported as “A gasket leak was found on the meter run. The meter run was isolated, the leak was stopped, and the gasket
was replaced. No liquids.
Gas loss volume based on: estimated Port size .250”, estimated average pressure during the event 88 psi, estimated duration 783 minutes.” |
03/15/2021 |
Release discovered by the operator. |