OCD Permitting

NAPP2213858200 LATERAL S 76 @ 0

General Incident Information
LATERAL S 76

[fAPP2123052765] HARVEST FOUR CORNERS GATHER SYSTEM
[373888] Harvest Four Corners, LLC
Cancellation Request Approved, Cancelled
Natural Gas Release

Aztec
Major
Jicarilla
Rio Arriba (39)

C-10-26N-04W      0 FNL      0 FEL
36.50656,-107.24206 NAD83


Notes

Industry Rep















Contact Details

Monica Smith

Event Dates

05/17/2022

6/1/2022

08/15/2022  

Incident Dates

Type Action Received Denied Approved
Cancellation Request 05/24/2022 05/24/2022
Notification 05/18/2022 05/18/2022

Compositional Analysis of Vented and/or Flared Natural Gas

No Compositional Analysis Found


Incident Materials

Cause Source Material Volume Units
Unk. Released Recovered Lost
Equipment Failure Pipeline (Any) Produced Water 0 0 0 BBL
Equipment Failure Pipeline (Any) Condensate 0 0 0 BBL
 
The concentration of dissolved chloride in the produced water >10,000 mg/l:           Yes           No        

Incident Events

Date Detail
05/24/2022 Incident cancelled due to discovery of pipeline ownership belong to High River Resources.
05/18/2022 The (05/18/2022, NOR) application [108450] was assigned to this incident.
05/18/2022 Operator indicated that immediate notice was given (05/17/2022) prior to the submission of the NOR.
05/18/2022 Initial Response question & answers at the time of notification were as follows.
  • The source of the release has been stopped: True.
  • The impacted area has been secured to protect human health and the environment: True.
  • Released materials have been contained via the use of berms or dikes, absorbent pads, or other containment devices: True.
  • All free liquids and recoverable materials have been removed and managed appropriately: True.
05/18/2022 New incident created by the operator, upon the submission of notification of release.
05/17/2022 Release discovered by the operator.

Incident Severity
Major release as defined by 19.15.29.7(A) NMAC?
Yes No
From paragraph A. Major release determine using:
        (1) an unauthorized release of a volume, excluding gases, of 25 barrels or more;
        (2) an unauthorized release of a volume that:
                (b) may with reasonable probability reach a watercourse.

Incident Corrective Actions

Initial Response

The source of the release has been stopped.
The impacted area has been secured to protect human health and the environment.
Released materials have been contained via the use of berms or dikes, absorbent pads, or other containment devices.
All free liquids and recoverable materials have been removed and managed appropriately.
If all the actions described above have not been undertaken, explain why:

         


No site characterization data was found for this incident.

No remediation plan data was found for this incident.

No active remediation deferral request was found for this incident.

No remediation closure report data was found for this incident.

No reclamation report data was found for this incident.

No re-vegetation report data was found for this incident.

Orders No Orders Found


Click to go back to top of page