| 12/13/2022 |
Corrective actions provided by the operator: MP flare volume high due to high sales gas line pressure (Lucid) and our two small VRUs not being strong enough to buck the high line pressure. Big unit is not moving the volume it should be moving. The LP flare volume was high due tank vent blower sending tank vapors to an already packed and over pressured MP system which causes the LP system to back up and have to route to flare. |
| 12/13/2022 |
Steps taken to prevent waste provided by the operator: MP flare volume high due to high sales gas line pressure (Lucid) and our two small VRUs not being strong enough to buck the high line pressure. Big unit is not moving the volume it should be moving. The LP flare volume was high due tank vent blower sending tank vapors to an already packed and over pressured MP system which causes the LP system to back up and have to route to flare. |
| 12/13/2022 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 11/30/2022 |
The (12/13/2022, C-129A) application [162673] was assigned to this incident. |
| 11/30/2022 |
The (11/30/2022, NOMVF) application [162669] was assigned to this incident. |
| 11/30/2022 |
New incident created by the operator, upon the submission of a notification of venting or flaring. |
| 11/29/2022 |
The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A. |