| 02/06/2023 |
Corrective actions provided by the operator: No corrective actions taken at this site. Third party took corrective actions |
| 02/06/2023 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 02/06/2023 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 02/06/2023 |
The (02/06/2023, C-129A) application [182981] was assigned to this incident. |
| 12/16/2022 |
Corrective actions provided by the operator: No corrective actions taken at this site. Third party took corrective actions |
| 12/16/2022 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 12/16/2022 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 12/16/2022 |
The (12/16/2022, C-129A) application [167633] was assigned to this incident. |
| 12/02/2022 |
The (12/02/2022, NOMVF) application [163293] was assigned to this incident. |
| 12/02/2022 |
New incident created by the operator, upon the submission of a notification of venting or flaring. |
| 12/01/2022 |
The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A. |