12/23/2022 |
Incident cancelled by the operator, upon the submission of a [C-129] Cancel Venting and/or Flaring (C-129C) report. |
12/23/2022 |
The (12/23/2022, C-129C) application [169716] was assigned to this incident. |
12/21/2022 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
12/21/2022 |
The (12/21/2022, C-129A) application [169418] was assigned to this incident. |
12/21/2022 |
The (12/21/2022, C-129) application [169399] was assigned to this incident. |
12/21/2022 |
Corrective actions provided by the operator: Review downtime events and work to eliminate events causing downtime. |
12/21/2022 |
Steps taken to prevent waste provided by the operator: Monitor in real time. When alarmed, identify and work to resolve source causing the downtime. |
12/21/2022 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
12/16/2022 |
The flaring of natural gas discovered by the operator. |