12/23/2022 |
Incident cancelled by the operator, upon the submission of a [C-129] Cancel Venting and/or Flaring (C-129C) report. |
12/23/2022 |
The (12/23/2022, C-129C) application [169719] was assigned to this incident. |
12/21/2022 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
12/21/2022 |
The (12/21/2022, C-129A) application [169419] was assigned to this incident. |
12/21/2022 |
The (12/21/2022, C-129) application [169406] was assigned to this incident. |
12/21/2022 |
Corrective actions provided by the operator: Corrective actions are not in our control and reliant on outside source(s) |
12/21/2022 |
Steps taken to prevent waste provided by the operator: Monitor in real time when applicable and verify 3rd party vendor is responding to downtime event |
12/21/2022 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
12/16/2022 |
The flaring of natural gas discovered by the operator. |