| 12/11/2023 |
App ID 258435: Remediation has met 19.15.29 NMAC requirements. Soil impacts exceeding the reclamation standards have been left in place and are required to meet 19.15.29.13D (1) NMAC once the site is no longer reasonably needed for production or subsequent drilling ops. |
| 12/11/2023 |
The (12/11/2023, C-141) application [258435] was accepted by OCD. The operator was emailed with details of this event. |
| 12/11/2023 |
An application [258435] was submitted to OCD for review. It was submitted, indicating that it was an: [C-141] Application for administrative approval of a release notification and corrective action The operator was emailed confirmation of this event. |
| 08/29/2023 |
The (12/11/2023, C-141) application [258435] was assigned to this incident. |
| 02/17/2023 |
The (02/17/2023, C-141) application [186527] was accepted by OCD. The operator was emailed with details of this event. |
| 02/17/2023 |
An application [186527] was submitted to OCD for review. It was submitted, indicating that it was an: [C-141] Application for administrative approval of a release notification and corrective action The operator was emailed confirmation of this event. |
| 02/15/2023 |
The (02/17/2023, C-141) application [186527] was assigned to this incident. |
| 02/02/2023 |
C-141 received on 2/15/2023 for release on 02/02/2023. The cause of the release was reported as “Water line developed leak. Fluid stayed on pad”. |
| 02/02/2023 |
The (02/02/2023, NOR) application [182078] was assigned to this incident. |
| 02/02/2023 |
Release discovered by the operator. |
| 02/02/2023 |
Additional Details provided by the operator: Operator arrived on site and saw water spraying from a main water line. A pin hole was created on a main 6" water line. 14.3 bbls released on pad. spill did not go offsite. 5 bbls recovered. Fluids remained onsite. Leak was stopped by isolating the line. |
| 02/02/2023 |
Initial Response question & answers at the time of notification were as follows. - The source of the release has been stopped: True.
- The impacted area has been secured to protect human health and the environment: True.
- Released materials have been contained via the use of berms or dikes, absorbent pads, or other containment devices: True.
- All free liquids and recoverable materials have been removed and managed appropriately: True.
|
| 02/02/2023 |
New incident created by the operator, upon the submission of notification of release. |