| 02/21/2023 |
Corrective actions provided by the operator: Standard PM. No way to avoid periodic downtime for maintenance/repairs to address unforeseen issues. |
| 02/21/2023 |
Primary Equipment identified by the operator (Tank (Any), with additional details: The location experienced a malfunction that was not anticipated and the flaring can be attributed to the downtime of the equipment/VRU) |
| 02/21/2023 |
Steps taken to prevent waste provided by the operator: Standard PM. Worked with vendor to coordinate service time and minimize downtime. |
| 02/21/2023 |
Incident updated by the operator, upon the submission of a amendment for venting of natural gas report. |
| 02/21/2023 |
The (02/21/2023, C-129A) application [188803] was assigned to this incident. |
| 02/12/2023 |
The (02/12/2023, NOMVF) application [185219] was assigned to this incident. |
| 02/12/2023 |
New incident created by the operator, upon the submission of a notification of venting or flaring. |
| 02/11/2023 |
The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A. |