02/16/2023 |
Corrective actions provided by the operator: Midstream to evaluate |
02/16/2023 |
Steps taken to prevent waste provided by the operator: Curtailment of Production |
02/16/2023 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
02/16/2023 |
The (02/16/2023, C-129A) application [186998] was assigned to this incident. |
02/16/2023 |
The (02/16/2023, C-129) application [186924] was assigned to this incident. |
02/16/2023 |
Corrective actions provided by the operator: Verify Eqp. Operating Set Point is within Normal Operating Range |
02/16/2023 |
Steps taken to prevent waste provided by the operator: Normal Operations |
02/16/2023 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
02/02/2023 |
The flaring of natural gas discovered by the operator. |