09/28/2023 |
Did not meet 19.15.29.12D (1a) NMAC. Forbearance granted on 09/28/2023. Deferral has met approval. |
09/28/2023 |
The (09/28/2023, C-141) application [262005] was accepted by OCD. The operator was emailed with details of this event. |
09/28/2023 |
An application [262005] was submitted to OCD for review. It was submitted, indicating that it was an: [C-141] Application for administrative approval of a release notification and corrective action The operator was emailed confirmation of this event. |
09/05/2023 |
The (09/28/2023, C-141) application [262005] was assigned to this incident. |
07/14/2023 |
90-day time extension request via email is approved. The Remediation Due date updated to October 16, 2023. |
05/03/2023 |
The (05/03/2023, C-141) application [212954] was accepted by OCD. The operator was emailed with details of this event. |
05/03/2023 |
An application [212954] was submitted to OCD for review. It was submitted, indicating that it was an: [C-141] Application for administrative approval of a release notification and corrective action The operator was emailed confirmation of this event. |
05/02/2023 |
The (05/03/2023, C-141) application [212954] was assigned to this incident. |
04/19/2023 |
The (04/19/2023, NOR) application [208945] was assigned to this incident. |
04/19/2023 |
Operator indicated that immediate notice was given (04/18/2023) prior to the submission of the NOR. |
04/19/2023 |
Initial Response question & answers at the time of notification were as follows. - The source of the release has been stopped: True.
- The impacted area has been secured to protect human health and the environment: True.
- Released materials have been contained via the use of berms or dikes, absorbent pads, or other containment devices: True.
- All free liquids and recoverable materials have been removed and managed appropriately: True.
|
04/19/2023 |
New incident created by the operator, upon the submission of notification of release. |
04/17/2023 |
C-141 received on 5/3/2023 for release on 04/17/2023. The cause of the release was reported as “PRV lifted prematurely, the set pressure was 500 psi. The valve was relieved at 332 psi. Gas vented for 15 minutes with approximately
one gallon of produced water misting onto the ground”. |
04/17/2023 |
Release discovered by the operator. |