| 01/12/2024 |
Corrective actions provided by the operator: No corrective actions taken at this site. Third party took corrective actions |
| 01/12/2024 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 01/12/2024 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 01/12/2024 |
The (01/12/2024, C-129A) application [303131] was assigned to this incident. |
| 11/08/2023 |
The (11/08/2023, C-129) application [284160] was assigned to this incident. |
| 11/08/2023 |
Corrective actions provided by the operator: No corrective actions taken at this site. Third party took corrective actions |
| 11/08/2023 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 11/08/2023 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
| 11/01/2023 |
The flaring of natural gas discovered by the operator. |