| 11/20/2023 |
Corrective actions provided by the operator: Review past occurrences and share lessons learned whether it be formation gas, equipment/operational failures, or facility design issues |
| 11/20/2023 |
Steps taken to prevent waste provided by the operator: Monitor in real time when applicable and when alarmed, identify and work to resolve the source causing the poor gas quality |
| 11/20/2023 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 11/20/2023 |
The (11/20/2023, C-129A) application [287430] was assigned to this incident. |
| 11/10/2023 |
The (11/10/2023, NOMVF) application [284516] was assigned to this incident. |
| 11/10/2023 |
New incident created by the operator, upon the submission of a notification of venting or flaring. |
| 11/09/2023 |
The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A. |