| 05/11/2024 |
Corrective actions provided by the operator: Corrective actions are not in our control and reliant on outside source(s) |
| 05/11/2024 |
Steps taken to prevent waste provided by the operator: Monitored event and volumes in real time when applicable and confirmed proper flare operating settings |
| 05/11/2024 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 05/11/2024 |
The (05/11/2024, C-129A) application [343175] was assigned to this incident. |
| 05/11/2024 |
The (05/11/2024, C-129A) application [343175] was assigned to this incident. |
| 05/01/2024 |
The (05/01/2024, NOMVF) application [339419] was assigned to this incident. |
| 05/01/2024 |
New incident created by the operator, upon the submission of a notification of venting or flaring. |
| 04/30/2024 |
The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A. |