| 06/03/2024 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 06/03/2024 |
The (06/03/2024, C-129A) application [350115] was assigned to this incident. |
| 06/03/2024 |
Corrective actions provided by the operator: Implement a scheduled maintenance program to avoid failures |
| 06/03/2024 |
Steps taken to prevent waste provided by the operator: Task is site specific but should have pre job planning meeting and look for ways to limit or avoid flaring |
| 06/03/2024 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 06/03/2024 |
The (06/03/2024, C-129A) application [350109] was assigned to this incident. |
| 05/29/2024 |
The (05/29/2024, NOMVF) application [348726] was assigned to this incident. |
| 05/29/2024 |
New incident created by the operator, upon the submission of a notification of venting or flaring. |
| 05/28/2024 |
The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A. |