| 12/20/2024 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 12/20/2024 |
The (12/20/2024, C-129A) application [414391] was assigned to this incident. |
| 12/19/2024 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 12/19/2024 |
The (12/19/2024, C-129A) application [413768] was assigned to this incident. |
| 12/18/2024 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 12/18/2024 |
The (12/18/2024, C-129A) application [413229] was assigned to this incident. |
| 12/17/2024 |
The (12/17/2024, C-129) application [412733] was assigned to this incident. |
| 12/17/2024 |
Corrective actions provided by the operator: No corrective actions, normal ops |
| 12/17/2024 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 12/17/2024 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
| 12/16/2024 |
The flaring of natural gas discovered by the operator. |