| 04/24/2025 |
Incident cancelled by the operator, upon the submission of a [C-129] Cancel Venting and/or Flaring (C-129C) report. |
| 04/24/2025 |
The (04/24/2025, C-129C) application [455508] was assigned to this incident. |
| 03/12/2025 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 03/12/2025 |
The (03/12/2025, C-129A) application [441544] was assigned to this incident. |
| 03/12/2025 |
The (03/12/2025, C-129) application [441532] was assigned to this incident. |
| 03/12/2025 |
Corrective actions provided by the operator: Event was intentional and no corrective action needed for this event |
| 03/12/2025 |
Steps taken to prevent waste provided by the operator: Monitored in real time when applicable and only flare long enough to establish adequete rate and pressure to sustain flowing conditions |
| 03/12/2025 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
| 03/06/2025 |
The flaring of natural gas discovered by the operator. |