| 05/07/2025 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 05/07/2025 |
The (05/07/2025, C-129A) application [459553] was assigned to this incident. |
| 03/31/2025 |
Corrective actions provided by the operator: No corrective actions, normal ops |
| 03/31/2025 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 03/31/2025 |
Incident updated by the operator, upon the submission of a amendment for venting of natural gas report. |
| 03/31/2025 |
The (03/31/2025, C-129A) application [447268] was assigned to this incident. |
| 03/25/2025 |
The (03/25/2025, NOMVF) application [445246] was assigned to this incident. |
| 03/25/2025 |
The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A. |
| 03/25/2025 |
New incident created by the operator, upon the submission of a notification of venting or flaring. |