| 07/07/2025 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 07/07/2025 |
The (07/07/2025, C-129A) application [481960] was assigned to this incident. |
| 06/20/2025 |
Corrective actions provided by the operator: No corrective actions, normal ops |
| 06/20/2025 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 06/20/2025 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 06/20/2025 |
The (06/20/2025, C-129A) application [477257] was assigned to this incident. |
| 06/18/2025 |
The (06/18/2025, C-129) application [476109] was assigned to this incident. |
| 06/18/2025 |
Corrective actions provided by the operator: No corrective actions, normal ops |
| 06/18/2025 |
Steps taken to prevent waste provided by the operator: Verify pressure settings to flare. |
| 06/18/2025 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
| 06/03/2025 |
The flaring of natural gas discovered by the operator. |