| 08/21/2025 |
Corrective actions provided by the operator: Corrective actions are not in our control and reliant on outside source(s) |
| 08/21/2025 |
Steps taken to prevent waste provided by the operator: Monitored event and volumes in real time when applicable and confirmed proper flare operating settings |
| 08/21/2025 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 08/21/2025 |
The (08/21/2025, C-129A) application [498160] was assigned to this incident. |
| 08/21/2025 |
The (08/21/2025, C-129) application [498157] was assigned to this incident. |
| 08/21/2025 |
Corrective actions provided by the operator: Implement a scheduled maintenance program to avoid failures |
| 08/21/2025 |
Steps taken to prevent waste provided by the operator: Task is site specific but should have pre job planning meeting and look for ways to limit or avoid flaring |
| 08/21/2025 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
| 08/14/2025 |
The flaring of natural gas discovered by the operator. |