08/25/2025

9/9/2025

11/24/2025  

Incident Dates

19.15.29 NMAC - RELEASES

Type Action Received Denied Approved
Sampling Notice [507235] 09/18/2025 09/18/2025
Sampling Notice [507233] 09/18/2025 09/18/2025
Sampling Notice [507230] 09/18/2025 09/18/2025
Sampling Notice [499883] 08/27/2025 08/27/2025
Sampling Notice [499879] 08/27/2025 08/27/2025
Sampling Notice [499878] 08/27/2025 08/27/2025
Sampling Notice [499873] 08/27/2025 08/27/2025
Deferral Request [537921] 12/26/2025
Liner Inspection Notice [532210] 12/05/2025 12/05/2025
Liner Inspection Notice [526545] 11/14/2025 11/14/2025
Remediation Plan [537921] 12/26/2025
Site Characterization [537921] 12/26/2025
Initial C-141 Report [499235] 08/26/2025 08/26/2025
Notification [499222] 08/26/2025 08/26/2025

19.15.30 NMAC - REMEDIATION

Type Action Received Denied Approved

Compositional Analysis of Vented and/or Flared Natural Gas

No Compositional Analysis Found


Incident Materials

Cause Source Material Volume Units
Unk. Released Recovered Lost
Equipment Failure Coupling Crude Oil 7 5 2 BBL
 
The concentration of dissolved chloride in the produced water >10,000 mg/l:           Yes           No        
Cause of Release OR Additional Details provided for materials released:
Vibration caused the nipple on the discharge side on the LACT to break

Incident Events

Date Detail
12/26/2025 An application [537921] was submitted to OCD for review. It was submitted, indicating that it was an: [C-141] Application for administrative approval of a release notification and corrective action The operator was emailed confirmation of this event.
12/26/2025 The (12/26/2025, C-141) application [537921] was assigned to this incident.
12/05/2025 The (12/05/2025, C-141L) application [532210] was assigned to this incident.
11/14/2025 The (11/14/2025, C-141L) application [526545] was assigned to this incident.
09/18/2025 The (09/18/2025, C-141N) application [507235] was assigned to this incident.
09/18/2025 The (09/18/2025, C-141N) application [507233] was assigned to this incident.
09/18/2025 The (09/18/2025, C-141N) application [507230] was assigned to this incident.
08/27/2025 The (08/27/2025, C-141N) application [499883] was assigned to this incident.
08/27/2025 The (08/27/2025, C-141N) application [499879] was assigned to this incident.
08/27/2025 The (08/27/2025, C-141N) application [499878] was assigned to this incident.
08/27/2025 The (08/27/2025, C-141N) application [499873] was assigned to this incident.
08/26/2025 Spill calculations and initial c141 are approved. A remediation closure report is due for submittal to the OCD within 90-days from the discovery of the release, no later than 11/24/2025.
08/26/2025 The (08/26/2025, C-141) application [499235] was accepted by OCD. The operator was emailed with details of this event.
08/26/2025 An application [499235] was submitted to OCD for review. It was submitted, indicating that it was an: [C-141] Application for administrative approval of a release notification and corrective action The operator was emailed confirmation of this event.
08/26/2025 The (08/26/2025, C-141) application [499235] was assigned to this incident.
08/26/2025 The (08/26/2025, NOR) application [499222] was assigned to this incident.
08/26/2025 New incident created by the operator, upon the submission of notification of release.
08/25/2025 Release discovered by the operator.

Incident Severity
Major release as defined by 19.15.29.7(A) NMAC?
Yes No

Incident Corrective Actions

Initial Response

The source of the release has been stopped.
The impacted area has been secured to protect human health and the environment.
Released materials have been contained via the use of berms or dikes, absorbent pads, or other containment devices.
All free liquids and recoverable materials have been removed and managed appropriately.
If all the actions described above have not been undertaken, explain why:

         


No site characterization data was found for this incident.

Remediation Plan

Have the lateral and vertical extents of contamination been fully delineated? Yes No
On what estimated date will the remediation commence?  
On what date will (or did) the final sampling occur?  
On what date will (or was) the remediation complete(d)  

Release is indicated as not yet fully delineated. Any Deferral Requests received may not be granted for this incident.

No remediation closure report data was found for this incident.

No reclamation report data was found for this incident.

No re-vegetation report data was found for this incident.