[fAPP2123031660] DCP SE NM Gathering System
[36785] DCP OPERATING COMPANY, LP
Active
Closure Not Approved, Pending submission of C-141 from the operator
Fire

I-10-24S-26E      0 FNL      0 FEL
32.23073,-104.27458 NAD83
Artesia
Private
Eddy (15)


Severity Indicators














Notes

Industry Rep
Referred to Environmental Inspector


Contact Details


Event Dates

11/15/2007

11/30/2007

11/13/2018  

Incident Dates

19.15.29 NMAC - RELEASES

Type Action Received Denied Approved
Remediation Closure Report Extension 08/15/2018 08/15/2018

19.15.30 NMAC - REMEDIATION

Type Action Received Denied Approved

Compositional Analysis of Vented and/or Flared Natural Gas

No Compositional Analysis Found


Incident Materials

No Materials Found


Incident Events

Date Detail
11/15/2007 Vapor cloud formed during pig operations and ignited. One employee in critical condition at Lubbock Burn Center. Investigation ongoing.

Incident Severity
Major release as defined by 19.15.29.7(A) NMAC?
Yes No
From paragraph A. Major release determine using:
        (2) an unauthorized release of a volume that:
                (a) results in a fire or is the result of a fire.

Incident Corrective Actions
No initial response data was found for this incident.

No site characterization data was found for this incident.

No remediation plan data was found for this incident.

No active remediation deferral request was found for this incident.

No remediation closure report data was found for this incident.

No reclamation report data was found for this incident.

No re-vegetation report data was found for this incident.

Orders No Orders Found