NRMD0929653187 WILLIAMS FOUR CORNERS, LLC @ 0

General Incident Information
WILLIAMS FOUR CORNERS, LLC

[fAPP2123052765] HARVEST FOUR CORNERS GATHER SYSTEM
[374105] Williams Four Corners, LLC
Incident Closure Approved
Natural Gas Release

Aztec
Major

San Juan (45)

6-24-32N-09W      0 FNL      0 FEL
36.96991,-107.73121 NAD83


Notes

Industry Rep















Contact Details


Event Dates

01/02/2008

1/17/2008

11/13/2018  

Incident Dates

Type Action Received Denied Approved
Remediation Closure Report 09/18/2023
Remediation Closure Report Extension 08/15/2018 08/15/2018
Initial C-141 Report 01/02/2008 01/02/2008

Compositional Analysis of Vented and/or Flared Natural Gas

No Compositional Analysis Found


Incident Materials

Cause Source Material Volume Units
Unk. Released Recovered Lost
Freeze Valve [OBSOLETE] Natural Gas (Methane) 782 0 782 Mcf
 
The concentration of dissolved chloride in the produced water >10,000 mg/l:           Yes           No        

Incident Events

Date Detail
09/18/2023 Historical incident review. Gas release only. Closure approved. Added GPS coordinates for center of STR to close.
10/23/2009 Valve pilot operator froze giving a false pressure reading, incorrect reading tripped pressure relief valve causing release. Final report received.

Incident Severity
Major release as defined by 19.15.29.7(A) NMAC?
Yes No
From paragraph A. Major release determine using:
        (3) an unauthorized release of gases exceeding 500 MCF.

Incident Corrective Actions
No initial response data was found for this incident.

No site characterization data was found for this incident.

No remediation plan data was found for this incident.

No active remediation deferral request was found for this incident.

No remediation closure report data was found for this incident.

No reclamation report data was found for this incident.

No re-vegetation report data was found for this incident.

Orders No Orders Found