OCD Permitting

NAPP2205355506 2022 MAJOR I FLAR @ 0

General Incident Information

[fAPP2122833205] Lakewood Federal Com South Tank Battery
[328947] Spur Energy Partners LLC
Inactive
Amended C-129 Accepted, Operator required to follow Monthly/Annual Waste Rule reporting requirements
Flare

D-03-20S-25E      0 FNL      0 FEL
32.608649,-104.479201 NAD83
Artesia
Eddy (15)


Severity Indicators














Notes

Industry Rep


Contact Details


Event Dates

02/21/2022
05:00 PM

02/21/2022
05:00 PM
3/8/2022

 

Incident Dates

19.15.29 NMAC - RELEASES

Type Action Received Denied Approved
Initial C-129 Report [84234] 02/25/2022 02/25/2022
Notification [83384] 02/22/2022 02/22/2022

19.15.30 NMAC - REMEDIATION

Type Action Received Denied Approved

Compositional Analysis of Vented and/or Flared Natural Gas

Date Methane
(CH4) %
Nitrogen
(N2) %
Hydrogen Suffide
(H2S) PPM
Carbon Dioxide
(CO2) %
Oxygen
(O2) %
Natural Gas Analysis 02/25/2022 52 6 19229 6 0

Incident Materials

Cause Source Material Volume Units
Unk. Released Recovered Lost
Other (Specify) 0 0 0
Pipeline Quality Specifications Other (Specify) Natural Gas Flared 1078 0 1078 Mcf
 
The concentration of dissolved chloride in the produced water >10,000 mg/l:           Yes           No        

Incident Events

Date Detail
02/25/2022 Corrective actions provided by the operator: Executed contract with midstream company to gather gas by 12/1/2021. Delays on approved ROWs have pushed the tie-in date to late March.
02/25/2022 Steps taken to prevent waste provided by the operator: Executed contract with midstream company to gather gas by 12/1/2021. Delays on approved ROWs have pushed the tie-in date to late March.
02/25/2022 Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report.
02/25/2022 The (02/25/2022, C-129A) application [84234] was assigned to this incident.
02/22/2022 The (02/22/2022, NOMVF) application [83384] was assigned to this incident.
02/22/2022 New incident created by the operator, upon the submission of a notification of venting or flaring.
02/21/2022 The event discovered by the operator; will be tracked as a Flare till submission of the required subsequent C-129A.

Incident Severity
Major release as defined by 19.15.29.7(A) NMAC?
Yes No

Incident Corrective Actions






Orders No Orders Found


Click to go back to top of page