OCD Permitting

NAPP2411277241 2024 MINOR CCRA FLAR @ 0

General Incident Information


[fAPP2126645866] CEDAR CANYON 22 CTB
[16696] OXY USA INC
Cancellation Request Accepted, Cancelled
Flare

Artesia
Minor

Eddy (15)

L-22-24S-29E      0 FNL      0 FEL
32.19971,-103.97784 NAD83


Notes

Industry Rep















Contact Details


Event Dates

04/06/2024
12:00 AM

04/06/2024
11:59 PM
4/22/2024

 

Incident Dates

Type Action Received Denied Approved
Cancellation Request [336497] 04/23/2024 04/23/2024
Initial C-129 Report [335704] 04/21/2024 04/21/2024
Notification [335704] 04/21/2024 04/21/2024

Compositional Analysis of Vented and/or Flared Natural Gas

Date Methane
(CH4) %
Nitrogen
(N2) %
Hydrogen Suffide
(H2S) PPM
Carbon Dioxide
(CO2) %
Oxygen
(O2) %
Natural Gas Analysis 04/21/2024 76 2 0 2 0

Incident Materials

Cause Source Material Volume Units
Unk. Released Recovered Lost
Other Other (Specify) Natural Gas Flared 72 0 72 Mcf
 
The concentration of dissolved chloride in the produced water >10,000 mg/l:           Yes           No        

Incident Events

Date Detail
04/23/2024 Incident cancelled by the operator, upon the submission of a [C-129] Cancel Venting and/or Flaring (C-129C) report.
04/23/2024 The (04/23/2024, C-129C) application [336497] was assigned to this incident.
04/21/2024 The (04/21/2024, C-129) application [335704] was assigned to this incident.
04/21/2024 Additional Details provided by the operator: Gas Flare Meter
04/21/2024 Corrective actions provided by the operator: Oxy is limited in the corrective actions to eliminate the cause and potential reoccurrence of a flash volume. Notwithstanding proper tank design and operation, various forms of mechanical or technical issues can be sudden, reasonably unforeseeable, and unexpected which can cause tank malfunctions to occur without warning or advance notice. Oxy continually strives to maintain and operate its facility equipment in a manner consistent with good practices for minimizing emissions and reducing the number of emission events. Oxy has a strong and positive equipment preventative maintenance program in place. The only actions that Oxy can take and handle that is within its control, is to keep continue with its equipment preventative maintenance program for this facility.
04/21/2024 Primary Equipment identified by the operator (Other (Specify), with additional details: Venting > Wedge Production > Flash Volume > OGS Oil Tank)
04/21/2024 Steps taken to prevent waste provided by the operator: In this case, wedge production led to more flash volume than anticipated via simulation, which then triggered venting to occur. When venting was identified, Operations immediately made changes to the heater setpoints and pressure settings to minimize flash to the tanks. In addition, field personnel will continue to monitor the pressure settings. All facility operations and equipment were working as designed prior to the sudden and without warning venting occurrence. This event was out Oxy’s control, yet every effort was made to minimize the emissions.
04/21/2024 New incident created by the operator, upon the submission of a flaring of natural gas report.
04/06/2024 The flaring of natural gas discovered by the operator.

Incident Severity
Major release as defined by 19.15.29.7(A) NMAC?
Yes No

Incident Corrective Actions






Orders No Orders Found


Click to go back to top of page