| 12/11/2025 |
Corrective actions provided by the operator: Corrective actions are not in our control and reliant on outside source(s) |
| 12/11/2025 |
Steps taken to prevent waste provided by the operator: Monitored event and volumes in real time when applicable and confirmed proper flare operating settings |
| 12/11/2025 |
Incident updated by the operator, upon the submission of a amendment for flaring of natural gas report. |
| 12/11/2025 |
The (12/11/2025, C-129A) application [534003] was assigned to this incident. |
| 12/11/2025 |
The (12/11/2025, C-129) application [534000] was assigned to this incident. |
| 12/11/2025 |
Corrective actions provided by the operator: Corrective actions are site specific but work to establish the best VRU run time |
| 12/11/2025 |
Steps taken to prevent waste provided by the operator: Event is site specific but if present, work to get VRU back on line |
| 12/11/2025 |
New incident created by the operator, upon the submission of a flaring of natural gas report. |
| 12/06/2025 |
The flaring of natural gas discovered by the operator. |